Sunset Square – JR Earthmoving

Manufacturing, Assembly and Painting of Metal Structures - Praça do Pôr do Sol, Boiçucanga

  • Client: JR Earthmoving (work for São Sebastião City Hall)
  • Location: Praça do Pôr do Sol, Boiçucanga – São Sebastião, SP
  • Period: Oct-Dec 2022 (2 months)
  • Category: CIVIL CONSTRUCTION

CONTEXT

JR Earthmoving contracted by the City Hall to modernize Praça do Pôr do Sol – emblematic seaside tourist spot.


THE PROPOSAL

Scope:

  • Manufacture 200+ tons of metal structures
  • Raw material processing
  • On-site assembly
  • Complete painting


Deadline:

  • 60 days from start to final delivery
  • Absolute deadline: December 23, 2022
  • Reason: City Hall wanted square ready before Christmas and New Year’s (hundreds of thousands of tourists)

 

THE PRESSURE

  • High-visibility project (seaside square, tourists, press)
  • Mayor personally overseeing (multiple visits)
  • No room for delays (political impact)

 

EXECUTION

30 MEN working simultaneously for 2 months:

Phase 1 – Workshop Fabrication (4 weeks):

  • Cutting, bending, drilling
  • Welding and assembly
  • Finishing and priming

Phase 2 – On-Site Assembly (3 weeks):

  • Transport (31 miles)
  • Lifting of large structures
  • Assembly and fastening
  • Field welding

Phase 3 – Final Painting (1 week):

  • Preparation
  • Application of complete system
  • Touch-ups

MAYOR’S VISITS

Mayor visited multiple times. Initially concerned: “Will we make it on time?”

With each visit, more at ease seeing organized progress.

 

HISTORIC DELIVERY

DECEMBER 23, 2022 – exactly as promised:

✅ All structures assembled
✅ Final painting completed
✅ Full cleanup
✅ Square ready

It was the eve of Christmas Eve. São Sebastião already crowded with tourists. People started taking pictures immediately.

 

IMPACT

Praça do Pôr do Sol is one of the most photographed spots in São Sebastião. Thousands of tourists annually. Structures impeccable after 3 years in a seaside environment.

 

RESULTS

✅ Deadline met EXACTLY (12/23/2022)
✅ 200+ tons manufactured/installed
✅ Structures perfect for 3+ years
✅ Zero accidents
✅ Permanent public visibility
✅ Mayor and client satisfied

 

DATA

  • Material: 200+ tons
  • Professionals: 30 (peak)
  • Duration: 2 months
  • Deadline: December 23, 2022 (met)
  • Location: Seaside
  • Visitors: Thousands annually
  • Status: Impeccable (2022-2025)

Your project demands absolute reliability. Engport delivers.

Certified team (ISO 9001, IRATA, AWS), track record of 150+ completed projects, and ability to operate in critical environments with Zero Downtime.
If you are looking for a flawless solution, on time and with full traceability, talk to our engineering team.