Complete Overhaul of Grabs 9m³, 12m³ and 15m³ - Fullport São Francisco do Sul
- Client: Fullport
- Location: São Francisco do Sul, SC → São Sebastião, SP
- Period: 2022 (6 months)
THE POWER OF REPUTATION
After success at Natrios, Fullport contacted us by referral: “We heard about the work on Natrios’ grab. We have 3 grabs that need complete maintenance.”
DIAGNOSIS
Grab 9m³: Never had preventive maintenance
Grab 12m³: Never had preventive maintenance
Grab 15m³: Never had preventive maintenance
All with critical wear, imminent risk of catastrophic failure.
COMPLEX LOGISTICS
Transporting 3 bulky grabs from Santa Catarina to São Sebastião (~1,700km) required special trailers and coordination of local traffic.
EXECUTION
3 SIMULTANEOUS TEAMS – one dedicated to each grab:
Each grab underwent:
- Complete disassembly
- Structural recovery
- Replacements (cables, pins, bushes, cylinders, hoses)
- Blasting and painting
- Complete testing
ASSISTED OPERATION
After refurbishment, our team traveled to Santa Catarina with each grab, monitored the first days of operation, ensuring success.
RESULTS
6 months (2 months/grab with overlap)
Zero accidents
100% tested and approved
Assisted operation – total success
Client returned 3 years later (Nov/2025)
DATA
- Equipment: 3 grabs (9m³, 12m³, 15m³)
- Teams: 3 simultaneous
- Duration: 6 months
- Distance: ~1,700km SC ↔ SP
- Replaced components: Hundreds
- Status: Operating perfectly for 3+ years