Manufacturing, Assembly and Painting of Metal Structures - Praça do Pôr do Sol, Boiçucanga
- Client: JR Earthmoving (work for São Sebastião City Hall)
- Location: Praça do Pôr do Sol, Boiçucanga – São Sebastião, SP
- Period: Oct-Dec 2022 (2 months)
- Category: CIVIL CONSTRUCTION
CONTEXT
JR Earthmoving contracted by the City Hall to modernize Praça do Pôr do Sol – emblematic seaside tourist spot.
THE PROPOSAL
Scope:
- Manufacture 200+ tons of metal structures
- Raw material processing
- On-site assembly
- Complete painting
Deadline:
- 60 days from start to final delivery
- Absolute deadline: December 23, 2022
- Reason: City Hall wanted square ready before Christmas and New Year’s (hundreds of thousands of tourists)
THE PRESSURE
- High-visibility project (seaside square, tourists, press)
- Mayor personally overseeing (multiple visits)
- No room for delays (political impact)
EXECUTION
30 MEN working simultaneously for 2 months:
Phase 1 – Workshop Fabrication (4 weeks):
- Cutting, bending, drilling
- Welding and assembly
- Finishing and priming
Phase 2 – On-Site Assembly (3 weeks):
- Transport (31 miles)
- Lifting of large structures
- Assembly and fastening
- Field welding
Phase 3 – Final Painting (1 week):
- Preparation
- Application of complete system
- Touch-ups
MAYOR’S VISITS
Mayor visited multiple times. Initially concerned: “Will we make it on time?”
With each visit, more at ease seeing organized progress.
HISTORIC DELIVERY
DECEMBER 23, 2022 – exactly as promised:
All structures assembled
Final painting completed
Full cleanup
Square ready
It was the eve of Christmas Eve. São Sebastião already crowded with tourists. People started taking pictures immediately.
IMPACT
Praça do Pôr do Sol is one of the most photographed spots in São Sebastião. Thousands of tourists annually. Structures impeccable after 3 years in a seaside environment.
RESULTS
Deadline met EXACTLY (12/23/2022)
200+ tons manufactured/installed
Structures perfect for 3+ years
Zero accidents
Permanent public visibility
Mayor and client satisfied
DATA
- Material: 200+ tons
- Professionals: 30 (peak)
- Duration: 2 months
- Deadline: December 23, 2022 (met)
- Location: Seaside
- Visitors: Thousands annually
- Status: Impeccable (2022-2025)